xViz
ProductPricingCommunity
  • Welcome to xViz Docs!
  • Project Management
    • Project Management - xViz Gantt Chart | Introduction
    • Hierarchy and Additional Columns
    • 🔸Milestones
      • Milestone Formatting
    • Planned Bars
      • Planned Bars Formatting
    • Connectors
      • Primary & Secondary Connectors
      • Multiple Connectors
      • Connectors Formatting
    • Progress
      • Tracking the progress
      • Progress Bar Display
      • Progress Base
      • Bar Formatting
    • Timeline Configurations
      • Timeline Start/End
      • Timeline Range
      • Header Levels
      • Zoom Levels
      • Zoom Options
      • Fiscal Year Support
      • Timeline Format
      • Language Support for Timeline
    • ✨Alerting Techniques
      • Steps to enable Conditional Formatting
      • Conditional Formatting
    • Reference Lines and Reference Range
      • Introduction
      • Static Approach
      • Data Driven Approach
    • Resource Gantt
    • ➡️Other Features
      • Data Colors
        • Row Background Color
        • Bar Border Color
        • Bar Selection Color
        • Bar Fill Color
        • Connectors
      • Duration Data field
      • Display Duration
      • Display Totals
      • Hide Blanks
      • Date Formats
      • DaysOff
        • Weekday
        • Custom Date
      • Setting Up Drill-through
      • Configure External URLs
      • Splitter Position
      • Text Customization
      • Row Numbering
      • Indentation
      • Sorting
    • Parent Level Calculations
      • Aggregation Types
    • Tooltip
    • Release Notes
    • ❓FAQs
  • Performance Management
    • Performance Flow - Introduction
      • Installing from AppSource
      • Get Started
    • Use Cases
      • Organization Performance
      • Microsoft Tenant Data Analytics
        • Organization Chart using Microsoft Graph API
      • Process Flow
      • Sales Performance Analysis
      • Cost Center Analysis
      • KPI Tree
      • Warehouse Management
      • Supply Chain Network
    • Configuring the chart structure
      • Hierarchy structure
      • Grouping / Swim Lanes
        • Data Structure for Columnar Group View
        • Data Structure for Wide Group Views
      • Invisible Group
    • 🪪Display Data in the Cards
      • Title, Subtitle
      • 👨‍💼Images
        • Converting HTTPs link images/icons to Base 64 in Power BI
        • Handling long Base 64 URLs in Power BI
      • 🔢Displaying KPIs
        • Number Formatting
      • 🔻Displaying Variance
      • Sparkline Trends
      • 🔗Hyperlinks
    • Card Formatting
      • Data-Driven Color
      • Templates
      • Customize Template
        • Insert additional data
        • Alignment
        • Wrap Text
        • Styling
        • Margin & Split
        • Modify (Delete / Cope-Paste)
        • Import/Export
    • Links
    • 🗒️Notes & Annotation
    • 🚦Conditional Formatting
    • Layout & Orientation
    • ✨Search
    • ✨Viewing Subtrees
      • Cross Filtering with Subtrees
    • 🔐✨User Context - RLS Experience
    • ✨Filter Context
    • 🎨Formatting Features
      • Formatting Font & Colors
      • Connectors
      • Expand Collapse Button
      • Dimensions
    • Toolbar Ribbon Configuration
    • Simulation
    • ❓FAQs
      • Circular Dependency message
    • Tips & Tricks
      • Bookmark
      • Report Page Tooltip
      • Field Parameters
      • Drill Through
    • Release Notes
Powered by GitBook
On this page

Was this helpful?

  1. Project Management
  2. Timeline Configurations

Zoom Options

PreviousZoom LevelsNextFiscal Year Support

Last updated 6 months ago

Was this helpful?

Enable report end-users to zoom the timeline easily by using Button or the Wheel options provided. It allows you to visualize the timeline at various levels of granularity.

To enable it: Go to the Format Pane -> Chart Options -> Zoom Options.

Set the Zoom options to either Button or Wheel for zooming.

To define which levels should appear on zooming in, set the “Zoom Leves” configuration explained in the earlier section of this document.

Image 1: Zoom Options
GIF 1: Zooming through the timeline using button option in xViz Gantt Chart